REF |
PROJECT NAME |
DETAILS |
PICTURE |
| 1 |
Rehabilitation of two
steam boilers . |
The object of the project is to
rehabilitate two out of four steam boiler to regain
Original capacity 160 t/h . They were originally constructed in
1983 .
The first boiler was rehabilitated by state company for heavy
machineries under
the supervision of an ltalion company . Now the work is done by
our cadres , some
specialised workers to be hired .
|
 |
| 2 |
Rchab. of compressors and
Turbines |
main compressor and their steam
turbines
of Train 1000 to be completely rehabilitated by NGC cadres ,
materials and
replacing parts are required .
|
 |
| 3 |
Moderanisation of control
systems |
All control systems to be
replaced . Old systems are obsolete . New DCS and
PLC systems are required
|
|
| 4 |
Developing industrial and
utility facilities . |
1-New buildings .
2-New warehouse facilities .
3-Manufacturing heat exchanges .
4- Manufacturing cooling tower cell's cones .
5-Other service facilities .
|
|
| 5 |
Moderanisation of fire fighting
systems . |
|
 |
| 6 |
Moderanisation of gas detecting
systems . |
|
|
| 7 |
Constructing two weighting
bridges for sulphur . |
|
|
| 8 |
Expanding water cooling system
by adding (3 – 5) new cells to the
existing cooling tower .
|
|
|
| 9 |
Moderanisation of the existing
Electricity Substations . |
|
|
| 10 |
Rehabilitation of waste water
treating unit . |
|
|
| 11 |
Import and construct electricity
generation unit (30 MW) . |
|
|